Objective

To use filter option to locate External Changes - Owner Changes in the project's Change Events tool using the Summary tab.

Steps

  1. Navigate to the project's Change Events tool.

  1. Click the Summary tab.

  1. Click Add Filter and select Type:

  1. Check the box beside Owner Change

  1. Press ESC on your keyboard to view the filtered list of change events.
  2. Select View beside a change
  3. Select pdf under Attachments to view the change.

Note:

  • Projected status: the change is still in Pricing stages
  • Pending status: the pricing letter has been submitted to the architect for review and approval
  • Approved status: the change has been approved.

Note: To clear one filter, click the X next to its name. OR To clear all filters, click Clear All.


For more information on Change Events, please refer to the coordinating manual linked below.

Operations Coordinating Manual

Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.

Still need help? Contact Us Contact Us